Can I Hold you to That?

Clients want to know how long software will take and what it costs. A look at the Jeffries and Fowler debate on estimation, and why neither fully satisfies.

Art+Logic Mar 5, 20132 min read

From the Art+Logic archive · written in 2013. The tools may have moved on; the thinking still holds.

Project Management Cartoon

I came across two articles over the past few days, both of which resonated with me, but neither of which filled me with much hope for a resolution to the problem they addressed.

Ron Jeffries’ article, Estimation is Evil: Overcoming the Estimation Obsession, enumerates some well-known issues with how software estimates are interpreted and the problems they cause. His suggestion is to forego estimation, start building software, and come to a go/no-go decision after a couple of iteration cycles.

Martin Fowler followed up Jeffries’ with his own post, PurposeOfEstimation. In it, Fowler says it may be better to only estimate items that require you to make a significant decision.

But as Jeffries states in his article:

It seems that “they” [clients] often want to know how long something is going to take, and how much it will cost…“they” are often powerful and have the money we need, so we need to answer their question, even though we cannot.

And usually “they” want the question answered before the work starts, the exact point in time when “…we know less about our project than we’ll ever know again.”

Ultimately, I think the issue comes down to client education about the estimation process and it’s weaknesses. Fowler touches on this when he quotes his colleague Angela Ferguson:

the way that estimates set expectations is up to us - it is poor project management (whether by project managers or other team members) that results in a client who thinks estimates are fixed, or that raw estimates = actual effort/duration

Even more important is building up trust with the client by delivering working software as early and frequently as possible. Establishing a pattern of delivering value to the client can create enough goodwill where the client can focus on the bigger picture and look past the inevitable misestimates that occur.

Convincing your client to forego an estimate before work begins, or taking the time to educate them that estimates are not guarantees, are both difficult tasks. Both the appropriate choice of strategy and success with either will vary from client to client. But I find it hard to envision an environment in which business concerns don’t require estimates to be made with some level of accuracy.

keep going

More to explore in Build New.

All Build New resources →
let's talk

Got a problem like this one?

Tell us what's stuck. A real person replies within one business day.

Talk to our team →

Talk to people who know software, not a sales script.

Your first call is with Aja, our VP of Sales. He'll help make sure you're solving the right problem. Here's what you'll cover together:

  1. What you're trying to accomplish

    The business goal first, then the technology.

  2. Possible approaches

    And the tradeoffs of each, in plain language.

  3. Risks you may not have considered

    Technical and business, before they cost you.

  4. Whether AI changes the math

    What's practical, and what's just hype for your project.

  5. Sensible next steps

    Even if the right next step is not us.

book-a-call.ics

Loading the scheduler…

Open the booking page →

Some problems are easier to explain in writing. Send us a few lines about what you're working on, and we'll reply within one business day. Helpful to include:

  1. What the software does, or should do
  2. What's stuck, or what's worrying you
  3. Any deadline or budget you have in mind
note.md

Loading the form…